The grading of the beachfront cottages began today. They started at the east end of the cottages and will be working west. We
anticipate the grading work to be complete by April 13
th. Starting April 9
th the irrigation tech will be
on site to work on the irrigation repairs, following behind the grading crew. Once the grading and irrigation repairs have been completed, the area will be
hydro mulch with
Bermuda grass seed. We
anticipate all this to be finished by April 20
th.