Wednesday, March 4, 2009

Reconstruction Update

I know it has been a few days since my last Blog, I apologize. Things are moving pretty fast and we are making great progress this will be a quick update as to where we stand right now.

4151 Pointe West Dr. - Is in flooring stage. The trim has been installed and Paint complete.

4241 Pointe West Dr. - Is in the last stage of Paint. Drywall has been hung, taped, floated & textured with the trim installed and first coat of paint applied.

4231 Pointe West Dr. - Is finishing up texture. The drywall has been hung, taped, floated and will be primed and ready for trim early next week.

4221 Pointe West Dr. - Is finishing up paint. The drywall has been hung, taped and floated. The trim has been installed and primed and the first coat of paint applied

4211 Pointe West Dr. - Is finishing up paint & is in flooring stage. the drywall is complete as well as the trim & primer.

4121 Pointe West Dr. - Is finishing up Paint and trim. The drywall is hung, taped, floated & textured.

26421 Cat Tail - Is Finishing up Texture. The drywall has been hung, taped and floated.

26451 Cat Tail - Is in Float stage. The drywall has been hung and taped.

26934 Baywater - Is in Texture stage. The drywall has been hung, taped, floated & the soffits are ready for paint.

27010 Estuary - Is in Texture stage. The drywall has been hung, taped, floated & the soffits are ready for paint.

27020 Estuary - Is in tape & float stage. The drywall has been hung & the soffits are ready for paint.

27030 Estuary - Is in tape & float stage. The drywall has been hung & the soffits will be complete and ready for paint today.

26501 Mangrove - Has had the insulation hung & in Sheetrock stage.

26501 Mangrove - Is in insulation stage & soffits are being worked on.

THE FOLLOWING BUILDINGS HAVE HAD A/C WORK DONE TO BOTH THE A/C UNITS AND A/C CLOSETS AND IS WAITING START-UP PLEASE KEEP IN MIND THAT THE ONLY A/C'S THAT HAVE BEEN WORKED ON UP TO THIS POINT ARE THE ONES THAT NEEDED TO BE REINSTALLED BECAUSE THEY WERE REMOVED FROM THE CLOSETS BY THE REMEDIATION CREW. THE A/C TECHNICIAN WILL be GOING BACK THROUGH TO INSURE THE REST ARE WORKING WHEN WE INITIATE START-UP.

26441 Cat Tail

26471 Cat Tail

26320 Cat Tail

26350 Cat Tail

4221 Cat Tail

4111 Pointe West Dr.

If your building is in flooring stage it should be completed with in the next couple of weeks. Please send me an email to schedule a time to perform your walk through. Send it to matthewprince@mrpandcompany.com in the subject line put your building and unit number/walk through. PLEASE ONLY USE THIS EMAIL IF YOU ARE SCHEDULING A WALK THROUGH OTHERWISE IF YOU HAVE QUESTIONS REGARDING YOUR BUILDING PLEASE USE mrpconstruction@rocketmail.com Thank you for your cooperation.


Side Note: We have written a protocol for securing these buildings and it is being followed. However I would like to reiterate this is a construction site and I can not be in every unit all the time. If you have anything of great value inside your unit it is recommended that you remove it until reconstruction is complete. This is just a precaution.

Also the above mentioned stages are set by the building. For example: If 7 units have finished paint and trim than the building is in flooring stage even though there are still 2 units finishing up paint.

Thank you to everyone for your patience and understanding. I feel very good about how things are going and the time in which we are getting things done.

Thanks again,

Matthew R. Prince
M.R. Prince & Company