Monday, March 16, 2009

Bay Water Update

This update is for the Baywater Buildings I will post one for the Villas next. I am hoping to have a unit by unit update at the end of this week.

26934 Baywater Dr. - This building just got its first coat of paint on the walls and trim. It will still need another coat of paint then the electrician will be in to reset outlets and check plugs. Then the carpet and flooring will be installed. After that the cleaning crew will be in and we will be ready for walk through. This building is about 2 1/2 weeks out

26010 Baywater Dr. - This building has trim installed and is in the process of getting its first coat of paint. this building is about 3 weeks out.

26020 Baywater Dr. - this building has been primed and needs trim, This building is about 4 weeks out.

26030 Baywater Dr, - This building has been primed and needs trim, This building is about 4 weeks out.

26501 Mangrove Dr. - This building has been insulated drywalled taped and floated and is in sanding stage.

26511 Mangrove Dr. - This building has been insulated and has been skimmed but not sanded

26540 Mangrove Dr. - This building has been insulated and is in Tape and float stage

26550 Mangrove Dr. - This building has been insulated and is in tape and float stage

26560 Baywater Dr. - This building has been insulated and is being drywalled

26570 Baywater Dr. - This building has had insulation hung and the sub floor is being repaired