Friday, March 27, 2009
Owner Storage Units
March 27, 2009 - April 30, 2009
Owners to remove and dispose of contents from Storage Units
Owner can also give notice to CCMC to have porter remove ruined contents
May 1, 2009 - May 8, 2009
Porters cut locks from remaining storage units and dispose of ruined contents
May 11, 2009
Owners can start using storage units
Thursday, March 26, 2009
Tuesday, March 24, 2009
WGIPOA March Meeting
The agenda was extensive and did not leave any time for Q&A at the end of the meeting. Click this link for the agenda:
Agenda: https://home.comcast.net/~alpetros/Agenda_032109.pdf
Jerry Mohn noted this is the 10 year anniversary of the WGIPOA. It formed in March 1999.
The GLO will wait 2 seasons before establishing the final 4.5 foot line.
HB911 - Otie Zapp presented a summary on the impact of this potential new legislation. Otie believes this will produce devestating effects for Galveston and its property owners. All those present were in agreement action is needed to ensure this legislation is not approved. Everyone may want to keep up to date on the progress of this bill. Please read this attachment. https://home.comcast.net/~alpetros/HBill_911.pdf
Karen Mahoney, District 6, City Council reported on several topics. Of interest was:
- The Recovery Committee would be presenting to City Council on April 9 and public comment will be held at Ball HS this Saturday.
- Bollard replacement is behind schedule. City Council will be discussing this at the next meeting. She asked that we call the police if vehicles are driving on the beach where not allowed.
- Illegal signs posted by contractors will be coming down.
Cheryl Johnson, Tax Assessor/Collector moderated a PowerPoint presentation and had several handouts that she believed should answer most questions about her department's responsibilities and upcoming legislation that could affect each of us.
https://home.comcast.net/~alpetros/Tax_Slides.pdf
https://home.comcast.net/~alpetros/Tax_Time.pdf
https://home.comcast.net/~alpetros/Tax_Legislation.pdf
https://home.comcast.net/~alpetros/HB3779.pdf
https://home.comcast.net/~alpetros/Taxpayers_Rights.pdf
One last handout was provided by Marty Bilek on the Ike Dike proposal
Monday, March 23, 2009
Friday, March 20, 2009
Thursday, March 19, 2009
March 19, 2009 Contruction Update
WGIPOA Meeting
4210 Silver Reef PBW#1, Galveston, TX 77554
TEL: 409-737-5768 FAX: 409-737-5951
Email: mohn@msn.com
To: West Galveston Island Property
Owners Association
____________________________
March 19, 2009
MARK YOUR CALENDARS FOR A GREAT WGIPOA MEETING 3/21!!
MEETING: The next meeting will be on March 21, beginning at 8:30 AM for coffee and donuts and 9:00 AM for the meeting at the Moody Gardens Hotel in the Vine Room (first floor).
PROGRAM: Cheryl Johnson, Galveston County Tax Assessor/Collector, will be our guest speaker. Her topic is twofold: A class on “Effectively Protesting Your Values” tax legislation bill during the Texas Legislation Session. Cheryl will share her Taxing Legislation booklet with everyone and to provide information on how your folks can make a difference and what to do. The public is invited so bring your neighbors and friends.
Thank you for your support and we hope to see you on March 21 at the Moody Gardens Hotel in the Vine Room, starting at 8:30 for coffee and donuts and at 9:00 AM for the meeting.
Monday, March 16, 2009
POA Update
New street signs are being installed
Cross over plans are nearing completion
New surveys required for dune crossover reconstruction
Corp of Engineers exposure if mechanical equipment used in dune area
Homeowners have submitted $91K of the over $900K first POA hurricane assessment
Hospitality subcommittee held its first conference call on 3-13-09
Chairman – Gene Fairbrother
New POA website vendor meeting on 3-17-09
Lagoon fountain repairs scheduled for this week
TexDot has approval to clean and re-grade various road side waterways
Have submitted supplemental information and awaiting insurance company funding schedule.
Bay Water Update
26934 Baywater Dr. - This building just got its first coat of paint on the walls and trim. It will still need another coat of paint then the electrician will be in to reset outlets and check plugs. Then the carpet and flooring will be installed. After that the cleaning crew will be in and we will be ready for walk through. This building is about 2 1/2 weeks out
26010 Baywater Dr. - This building has trim installed and is in the process of getting its first coat of paint. this building is about 3 weeks out.
26020 Baywater Dr. - this building has been primed and needs trim, This building is about 4 weeks out.
26030 Baywater Dr, - This building has been primed and needs trim, This building is about 4 weeks out.
26501 Mangrove Dr. - This building has been insulated drywalled taped and floated and is in sanding stage.
26511 Mangrove Dr. - This building has been insulated and has been skimmed but not sanded
26540 Mangrove Dr. - This building has been insulated and is in Tape and float stage
26550 Mangrove Dr. - This building has been insulated and is in tape and float stage
26560 Baywater Dr. - This building has been insulated and is being drywalled
26570 Baywater Dr. - This building has had insulation hung and the sub floor is being repaired
Friday, March 6, 2009
Flood Insurance Update
Wednesday, March 4, 2009
Reconstruction Update
4151 Pointe West Dr. - Is in flooring stage. The trim has been installed and Paint complete.
4241 Pointe West Dr. - Is in the last stage of Paint. Drywall has been hung, taped, floated & textured with the trim installed and first coat of paint applied.
4231 Pointe West Dr. - Is finishing up texture. The drywall has been hung, taped, floated and will be primed and ready for trim early next week.
4221 Pointe West Dr. - Is finishing up paint. The drywall has been hung, taped and floated. The trim has been installed and primed and the first coat of paint applied
4211 Pointe West Dr. - Is finishing up paint & is in flooring stage. the drywall is complete as well as the trim & primer.
4121 Pointe West Dr. - Is finishing up Paint and trim. The drywall is hung, taped, floated & textured.
26421 Cat Tail - Is Finishing up Texture. The drywall has been hung, taped and floated.
26451 Cat Tail - Is in Float stage. The drywall has been hung and taped.
26934 Baywater - Is in Texture stage. The drywall has been hung, taped, floated & the soffits are ready for paint.
27010 Estuary - Is in Texture stage. The drywall has been hung, taped, floated & the soffits are ready for paint.
27020 Estuary - Is in tape & float stage. The drywall has been hung & the soffits are ready for paint.
27030 Estuary - Is in tape & float stage. The drywall has been hung & the soffits will be complete and ready for paint today.
26501 Mangrove - Has had the insulation hung & in Sheetrock stage.
26501 Mangrove - Is in insulation stage & soffits are being worked on.
THE FOLLOWING BUILDINGS HAVE HAD A/C WORK DONE TO BOTH THE A/C UNITS AND A/C CLOSETS AND IS WAITING START-UP PLEASE KEEP IN MIND THAT THE ONLY A/C'S THAT HAVE BEEN WORKED ON UP TO THIS POINT ARE THE ONES THAT NEEDED TO BE REINSTALLED BECAUSE THEY WERE REMOVED FROM THE CLOSETS BY THE REMEDIATION CREW. THE A/C TECHNICIAN WILL be GOING BACK THROUGH TO INSURE THE REST ARE WORKING WHEN WE INITIATE START-UP.
26441 Cat Tail
26471 Cat Tail
26320 Cat Tail
26350 Cat Tail
4221 Cat Tail
4111 Pointe West Dr.
If your building is in flooring stage it should be completed with in the next couple of weeks. Please send me an email to schedule a time to perform your walk through. Send it to matthewprince@mrpandcompany.com in the subject line put your building and unit number/walk through. PLEASE ONLY USE THIS EMAIL IF YOU ARE SCHEDULING A WALK THROUGH OTHERWISE IF YOU HAVE QUESTIONS REGARDING YOUR BUILDING PLEASE USE mrpconstruction@rocketmail.com Thank you for your cooperation.
Side Note: We have written a protocol for securing these buildings and it is being followed. However I would like to reiterate this is a construction site and I can not be in every unit all the time. If you have anything of great value inside your unit it is recommended that you remove it until reconstruction is complete. This is just a precaution.
Also the above mentioned stages are set by the building. For example: If 7 units have finished paint and trim than the building is in flooring stage even though there are still 2 units finishing up paint.
Thank you to everyone for your patience and understanding. I feel very good about how things are going and the time in which we are getting things done.
Thanks again,
Matthew R. Prince
M.R. Prince & Company