Saturday, February 14, 2009

reconstruction update

I wanted to let everyone know that things are moving along very well for our first week we currently are replacing the balcony ceilings in the following buildings:

26934 Baywater Dr.
27010 Estuary Dr.
27020 Estuary Dr.
27030 Estuary Dr.
26451 Cat Tail Dr.
26421 Cat Tail Dr.

And we have installed vertical wall insulation and have started the drywall phase in the following buildings:

4221 Pointe West Dr.
4231 Pointe West Dr.
4241 Pointe West Dr.
4121 Pointe West Dr.
4151 Pointe West Dr.

We are also walking the individual to insure that all material that needs to be removed is taken out before we are finished with build back. There will be a crew out next week to take care of these issues.